The structure was supported by a number of steel columns and beams and the roof was supported by timber joists covered using insulated panel monopitch roof sheets.
The internal walls were then plastered and painted, a new suspended ceiling throughout allowed electrical trunking and other cables to be concealed above it. Floor finishes and internal fittings were then completed to the School’s requirements.

The final stage of the contract was then completed during the School’s summer shutdown with the existing Reception being demolished and a new opening formed between the new link and existing building to allow fire doors and glazed screens to be installed.
The existing electrical trunking, fire alarm and intruder panel were altered and relocated and the new Reception wired for IT and Data. The front entrance doors were fitted with a new entry system that could be operated by key fob or a door release mechanism in the Reception Office only.
Value £210,000
|